SCOPE OF WORKS

Industrial subdivision at the old “Brick Works” quarry including:

  • Clearing and grubbing of 24 hectare site
  • 350,000m3 cut to fill bulk earthworks
  • Sort and re-compact 70,000m3 of uncontrolled fill
  • 30,000m3 of contaminated soil and buried rubbish removed from site
  • Muck out dams and dry and place 25,000m3 of saturated fill material
  • Construct approximately 1km of clean water diversion drains
  • Design and construct 8 metre + high soil nail walls
  • Design and construct 3 metre high rock retaining wall
  • Design and construct 5 metre high Magnum Stone Mass Block retaining wall