SCOPE OF WORKS

 

We completed the residential subdivision, major road works and wetlands. Specifically:

  • Construction of a 1000+ lot subdivision including 70 hectares of parks and wetlands
  • Clearing and grubbing
  • 300,000m3 of earthworks
  • New Main Roads intersections and roundabout
  • Over 10km of sewer and stormwater

PROJECT SPECIFIC REQUIREMENTS

Due to the location just 500m from the beach, tidal water was found when installing deep services. Most of the Black’s Beach development was built on sand, which made earthworks relatively easy to carry out and allowed us to continue working through the wet season in some instances.